Subapi 集成风险控制实施任务单(两周执行版,v1.5)
- 版本:v1.5
- 日期:2026-03-27
- 执行窗口:2026-03-18 至 2026-03-31(两周)
- 关联文档:
subapi_integration_compat_security_reliability_design_v1_2026-03-17.mdsubapi_expert_review_wargame_plan_v1_2026-03-17.mdrouter_core_takeover_execution_plan_v3_2026-03-17.mdrouter_core_takeover_metrics_sql_dashboard_v1_2026-03-17.mdrouter_core_s2_acceptance_test_cases_v1_2026-03-17.mdacceptance_gate_single_source_v1_2026-03-18.md(v1.1, 2026-03-24)llm_gateway_subapi_evolution_plan_v4_2_2026-03-24.mdsupply_button_level_prd_v1_2026-03-25.md(v1.1 冻结,2026-03-27)supply_api_contract_openapi_draft_v1_2026-03-25.yamlsupply_ui_test_cases_executable_v1_2026-03-25.mdsupply_gate_command_playbook_v1_2026-03-25.mdsupply_technical_design_enhanced_v1_2026-03-25.mdsupply_test_plan_enhanced_v1_2026-03-25.mdsupply_uiux_design_spec_v1_2026-03-25.mddatabase_domain_model_and_governance_v1_2026-03-27.mddependency_compatibility_audit_baseline_v1_2026-03-27.mdtests/supply/ui_design_qa_cases_v1_2026-03-25.mdreports/supply_gate_preflight_2026-03-25.mdreview/multi_expert_planning_review_v1_2026-03-25.md
1. 执行目标(两周必须达成)
- 建立 subapi 升级“兼容三重 Gate”(Schema/Behavior/Performance)并接入发布前闸门。
- 完成生产配置硬化,消除已识别高风险默认项。
- 建立安全告警和回滚演练闭环,确保 30 分钟内可回切。
- 将风险控制纳入日常运维流程,避免靠临时人工判断。
- 建立“凭证边界”硬门禁:需求方仅用平台凭证,供应方上游凭证零外发。
- 建立供应侧发布门禁链路(SUP):账号挂载 -> 套餐发布 -> 结算提现全链路可验收。
- 建立四专家整改发布链路(XR):技术/测试/UIUX/业主条款与门禁统一闭环。
- 建立 token 运行态交付链路(TOK):从实现、部署到门禁验收可追踪闭环。
2. 责任角色映射(实名RACI)
| 角色 | 实名负责人(主/备) | 职责 |
|---|---|---|
ARCH(架构负责人) |
王磊 / 赵凯 | 兼容策略、闸门标准、最终技术裁决 |
PLAT(平台工程) |
李娜 / 陈涛 | 流水线、配置发布、网关接入改造 |
SEC(安全负责人) |
周敏 / 郭强 | 安全基线、威胁验证、告警策略 |
SRE(稳定性负责人) |
刘洋 / 韩雪 | 监控、演练、故障响应与回滚 |
QA(测试负责人) |
孙悦 / 吴航 | 契约回归、流式边界、验收报告 |
FIN(计费/数据) |
何静 / 彭程 | 对账、幂等冲突监控、成本异常告警 |
说明:任务表中的角色标识(ARCH/PLAT/SEC/SRE/QA/FIN)按本表实名映射执行,并纳入 on-call 值班表。
3. 两周里程碑(绝对日期)
| 里程碑 | 截止日期 | 验收条件 |
|---|---|---|
| M1:基线冻结 | 2026-03-20 | 风险清单冻结;硬化项可检测 |
| M2:兼容闸门联通 | 2026-03-24 | 三重 Gate 在 CI 可执行并有报告 |
| M3:安全硬化完成 | 2026-03-27 | 高风险默认项全部改为生产安全值 |
| M4:回滚演练通过 | 2026-03-30 | 升级失败自动回退演练完成 |
| M5:两周验收 | 2026-03-31 | 交付证据包齐全并评审通过 |
4. 任务清单(可直接排期)
4.1 Workstream A:兼容性 Gate
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| COMP-001 | 固化 canonical 端点矩阵(OpenAI/Anthropic/Gemini) | ARCH + QA |
2026-03-19 | 无 | 端点矩阵冻结并评审通过 | docs/compat/canonical_endpoint_matrix.md |
| COMP-002 | 产出 Schema Gate 用例(请求/响应/错误结构) | QA |
2026-03-21 | COMP-001 | 覆盖核心 6 条链路;失败可定位到字段级 | tests/compat/schema_gate_report.md |
| COMP-003 | 产出 Behavior Gate 用例(流式/no-replay/重试) | QA |
2026-03-22 | COMP-001 | 覆盖流式边界与错误语义;无歧义 case | tests/compat/behavior_gate_report.md |
| COMP-004 | 产出 Performance Gate 阈值脚本(P95/5xx/账务) | SRE + FIN |
2026-03-23 | COMP-001 | 阈值可配置,支持阻断 | scripts/gate/perf_gate_check.sh |
| COMP-005 | 三重 Gate 接入发布流水线 | PLAT |
2026-03-24 | COMP-002/003/004 | 发布前自动执行,任一失败阻断发布 | CI 记录 + Gate 汇总报告 |
| COMP-006 | 定义兼容风险分级处置(P0/P1/P2) | ARCH |
2026-03-24 | COMP-005 | 每级别有明确响应时限与动作 | docs/compat/risk_severity_playbook.md |
| COMP-007 | 主路径 SQL 与 canonical 契约对齐(移除 alias/空端点歧义) | ARCH + FIN |
2026-03-22 | COMP-001 | 验收分母仅包含 canonical 主路径 | sql/takeover_main_path_canonical.sql |
| COMP-008 | 国内平台清单配置化(替代 SQL 硬编码) | PLAT + FIN |
2026-03-22 | COMP-007 | cn_platforms 来自配置表/配置中心 |
docs/compat/cn_platform_mapping.md |
| COMP-009 | Wave Gate 增加 route_mark_coverage>=99.9% 硬门槛 |
ARCH + QA |
2026-03-23 | COMP-007 | 覆盖率不达标自动 Stop | Wave Gate 配置快照 + 演练记录 |
4.2 Workstream B:安全硬化
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| SEC-001 | 生产配置扫描器(检测高风险默认项) | SEC + PLAT |
2026-03-20 | 无 | 可检测 run_mode/url_allowlist/private/http/trusted_proxies | scripts/security/config_hardening_scan.sh |
| SEC-002 | 生产环境配置硬化发布(标准模式+URL 策略) | PLAT |
2026-03-25 | SEC-001 | 所有环境通过扫描,无高危项 | 发布变更单 + 前后配置 diff |
| SEC-003 | 北向入口 query key 全拦截策略上线 | PLAT + SEC |
2026-03-25 | SEC-001 | 外部 query key 请求全部拒绝并告警 | 网关策略配置 + 拦截日志样本 |
| SEC-004 | Gemini 兼容请求 header 改写策略(内转) | PLAT |
2026-03-26 | SEC-003 | 兼容客户端可用,且不暴露 query key 通路 | 联调记录 + 回归测试报告 |
| SEC-005 | 出网 egress allowlist 与私网访问阻断 | SEC + SRE |
2026-03-27 | SEC-002 | 未授权域名/私网访问被阻断 | 防火墙/代理策略快照 + 拦截告警 |
| SEC-006 | ToS 合规审查记录归档(法务接口) | SEC |
2026-03-27 | 无 | 上游条款风险有书面结论 | compliance/subapi_tos_assessment_2026-03-27.pdf |
| SEC-007 | subapi 内网隔离与公网不可达验证 | SEC + SRE |
2026-03-20 | SEC-001 | subapi 服务不对公网开放,扫描验证通过 | 网络策略清单 + 连通性测试报告 |
| SEC-008 | 网关<->subapi mTLS 双向认证与证书轮换演练 | PLAT + SEC |
2026-03-24 | SEC-007 | 双向证书校验生效,轮换不影响可用性 | mTLS 配置 + 轮换演练报告 |
| SEC-009 | query key 外拒内转策略强制测试 | SEC + QA |
2026-03-27 | SEC-003, SEC-004 | 外部 query key 全拒绝,内部改写链路可追踪 | tests/security/query_key_boundary_report.md |
| SEC-010 | 供应方上游凭证泄露扫描与脱敏基线 | SEC + PLAT |
2026-03-26 | SEC-002 | supplier_credential_exposure_events=0,日志/报表无敏感片段 |
tests/security/credential_exposure_scan_report.md |
| SEC-011 | 需求方绕过平台直连供应方检测策略上线 | SEC + SRE |
2026-03-27 | SEC-005 | direct_supplier_call_by_consumer_events=0 可观测可告警 |
docs/security/direct_supplier_call_detection_v1.md |
| SEC-012 | 平台凭证入站覆盖率审计任务 | PLAT + SEC |
2026-03-26 | SEC-003 | platform_credential_ingress_coverage_pct=100% |
reports/security/platform_credential_ingress_coverage_2026-03-26.md |
4.3 Workstream C:运维简单与可靠性
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| REL-001 | 单一控制面发布流程定义(变更入口统一) | ARCH + PLAT |
2026-03-21 | 无 | 路由开关/灰度/熔断统一入口 | docs/ops/unified_change_flow.md |
| REL-002 | 安全+兼容+质量告警看板搭建 | SRE |
2026-03-26 | COMP-005, SEC-002 | 包含 query key、SSRF、冲突率、takeover | 看板截图 + 指标定义清单 |
| REL-003 | 回滚自动化脚本(版本回切) | PLAT + SRE |
2026-03-27 | COMP-005 | 10 分钟内触发回切,30 分钟内恢复 | scripts/release/rollback_subapi.sh + 演练日志 |
| REL-004 | Runbook 标准化(告警->判断->操作->验证) | SRE |
2026-03-28 | REL-002 | 至少覆盖 8 类高频告警 | docs/runbook/subapi_integration_runbook_v1.md |
| REL-005 | 一次完整演练(升级失败自动回退) | SRE + QA |
2026-03-30 | REL-003, REL-004 | 演练成功且复盘闭环 | 演练记录 + 复盘报告 |
| REL-006 | 两周验收评审与风险复盘 | ARCH + 全员 |
2026-03-31 | 全部任务 | 验收结论明确(通过/有条件通过/不通过) | reports/sprint_risk_control_review_2026-03-31.md |
| REL-007 | 凭证边界告警看板(M-013~M-016) | SRE + SEC |
2026-03-27 | SEC-010, SEC-011, SEC-012 | 凭证边界指标分钟级可观测并支持阈值告警 | 看板截图 + 告警策略快照 |
4.4 Workstream D:专家审核与博弈
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| EXP-001 | 确认专家名单与角色回避规则 | ARCH + SEC |
2026-03-18 | 无 | 专家名单冻结(含用户代表/测试专家/网关专家),独立性规则确认 | review/experts_roster_2026-03-18.md |
| EXP-002 | Round-1 架构与替换路径评审 | ARCH |
2026-03-19 | EXP-001 | 形成问题清单与决策建议 | review/rounds/round1_architecture_review.md |
| EXP-003 | Round-2 兼容与账务一致性评审 | QA + FIN |
2026-03-22 | COMP-002, COMP-003 | 兼容差异与账务风险可追踪 | review/rounds/round2_compat_billing_review.md |
| EXP-004 | Round-3 安全与合规攻防评审 | SEC |
2026-03-25 | SEC-002, SEC-003 | 安全/合规 P0 是否清零有明确结论 | review/rounds/round3_security_compliance_review.md |
| EXP-005 | Round-4 可靠性与回滚演练评审 | SRE |
2026-03-29 | REL-003, REL-004 | 演练满足 30 分钟恢复目标 | review/rounds/round4_reliability_wargame_review.md |
| EXP-006 | 专家最终决议(GO/CONDITIONAL GO/NO-GO) | ARCH + 管理层 |
2026-03-31 | EXP-002~005 | 决议与风险接受记录齐全 | review/final_decision_2026-03-31.md |
4.5 Workstream E:产品与项目治理闭环(新增)
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| PROD-001 | 迁移异常客户沟通模板与分级机制 | 产品 + CS |
2026-03-24 | EXP-002 | 迁移异常 30 分钟内有标准对外沟通 | docs/product/migration_incident_comms_v1.md |
| PROD-002 | 账务争议 SLA 与补偿边界定义 | 产品 + FIN + 法务 |
2026-03-24 | EXP-003 | 客户争议处理时限与补偿规则可执行 | docs/product/billing_dispute_sla_v1.md |
| PMO-001 | 任务实名 RACI 与备份负责人落地 | PMO + ARCH |
2026-03-18 | 无 | 所有 P0/P1 任务均有 owner+backup | reports/raci_snapshot_2026-03-18.md |
4.6 Workstream F:三角色联合评审落地(用户/测试/网关)
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| UXR-001 | 用户代表迁移旅程验收走查(含告警通知链路) | 产品 + CS + 用户代表 |
2026-03-25 | PROD-001 | 迁移异常场景 15 分钟内通知链路实测通过 | reports/user_representative_migration_walkthrough_2026-03-25.md |
| UXR-002 | 用户代表账务争议流程演练与反馈闭环 | 产品 + FIN + 用户代表 |
2026-03-25 | PROD-002 | 争议流程演练通过且用户侧反馈关闭 | reports/user_billing_dispute_drill_2026-03-25.md |
| TST-001 | 契约漂移检测接入 CI 阻断 | QA + PLAT |
2026-03-25 | COMP-005 | 漂移失败自动阻断发布 | tests/compat/contract_drift_ci_report.md |
| TST-002 | 流式+Failover 高压回归套件落地 | QA + SRE |
2026-03-27 | COMP-003, REL-002 | no-replay 与切换策略在高压下稳定通过 | tests/compat/stream_failover_stress_report.md |
| TST-003 | 升波证据包模板标准化 | QA + SRE |
2026-03-23 | COMP-009 | 每次升波均产出统一证据包 | evidence/*/wave_gate_bundle.md |
| TST-004 | 凭证边界回归测试(平台凭证入站/上游凭证不外发) | QA + SEC |
2026-03-27 | SEC-010, SEC-012 | 用例失败自动阻断发布 | tests/security/credential_boundary_regression_report.md |
| GAT-001 | Provider 能力矩阵与缺口清单 | ARCH + PLAT |
2026-03-22 | COMP-001 | 已接入供应商能力矩阵覆盖率 100% | docs/gateway/provider_capability_matrix_v1.md |
| GAT-002 | 三层降级策略与演练脚本 | ARCH + SRE |
2026-03-28 | REL-003 | 演练可在 30 分钟内止血恢复 | docs/gateway/degrade_playbook_v1.md |
| GAT-003 | Adapter SPI 版本兼容规范 | ARCH |
2026-03-26 | GAT-001 | 新增适配器均有 SPI 兼容校验 | docs/gateway/adapter_spi_versioning_v1.md |
| EXP-007 | 三角色联合复审(用户/测试/网关) | ARCH + QA + 产品 |
2026-03-27 | UXR-001, TST-001, GAT-001 | 形成联合复审结论并决定是否继续升波 | docs/subapi_role_based_review_wargame_optimization_v1_2026-03-18.md |
4.7 Workstream G:供应侧发布门禁链路(SUP,新增)
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| SUP-001 | 供应侧按钮级 PRD 冻结(3 页面) | 产品 + ARCH |
2026-03-26 | 无 | 页面字段、按钮、状态机、错误码冻结 | docs/supply_button_level_prd_v1_2026-03-25.md(v1.1 冻结) |
| SUP-002 | 供应侧 OpenAPI 契约冻结(3 页面) | PLAT + ARCH |
2026-03-26 | SUP-001 | 请求/响应字段、枚举、错误码冻结 | docs/supply_api_contract_openapi_draft_v1_2026-03-25.yaml |
| SUP-003 | UI-SUP 可执行用例评审通过 | QA + 产品 |
2026-03-27 | SUP-001, SUP-002 | UI-SUP-* + UI-DESIGN-QA-* 全量可执行,覆盖按钮/状态/权限/可访问性 |
docs/supply_ui_test_cases_executable_v1_2026-03-25.md + tests/supply/ui_design_qa_cases_v1_2026-03-25.md |
| SUP-004 | 账号挂载链路联调(验证/创建/激活/暂停) | PLAT + QA |
2026-03-28 | SUP-002, SUP-003 | UI-SUP-ACC-001~006 通过率 100% |
scripts/supply-gate/sup004_accounts.sh + tests/supply/ui_sup_acc_report_2026-03-28.md |
| SUP-005 | 套餐发布链路联调(草稿/上架/暂停/下架/复制) | PLAT + QA |
2026-03-29 | SUP-002, SUP-003 | UI-SUP-PKG-001~006 通过率 100% |
scripts/supply-gate/sup005_packages.sh + tests/supply/ui_sup_pkg_report_2026-03-29.md |
| SUP-006 | 结算提现链路联调(刷新/提现/撤销/导出) | PLAT + FIN + QA |
2026-03-29 | SUP-002, SUP-003 | UI-SUP-SET-001~005 通过率 100%,状态机无跳态 |
scripts/supply-gate/sup006_settlements.sh + tests/supply/ui_sup_set_report_2026-03-29.md |
| SUP-007 | 供应侧凭证边界专项回归(SEC-SUP) | SEC + QA |
2026-03-30 | SUP-004, SUP-005, SUP-006 | SEC-SUP-001~002 通过,M-013~M-016 持续达标 |
scripts/supply-gate/sup007_boundary.sh + tests/supply/sec_sup_boundary_report_2026-03-30.md |
| SUP-008 | 供应侧 Gate 汇总与发布结论 | ARCH + QA + 产品 |
2026-03-31 | SUP-004~SUP-007 | SUP Gate 结论为通过或有条件通过 | reports/supply_gate_review_2026-03-31.md |
4.8 Workstream H:四专家整改与复核链路(XR,新增)
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| XR-001 | 供应侧技术设计增强落地(幂等/并发/不变量/事务) | ARCH + PLAT |
2026-03-26 | SUP-002 | 关键写路径均具备双键幂等和冲突语义 | docs/supply_technical_design_enhanced_v1_2026-03-25.md |
| XR-002 | 供应侧测试方案增强落地(追踪矩阵+并发重放) | QA + ARCH |
2026-03-27 | XR-001 | Requirement->API->Test->Metric->Gate 全量可追踪,且路径一致性检查通过 | docs/supply_test_plan_enhanced_v1_2026-03-25.md + reports/supply_traceability_matrix_2026-03-25.csv + docs/supply_traceability_matrix_generation_rules_v1_2026-03-27.md + reports/supply_flaky_budget_2026-03-25.md |
| XR-003 | 供应侧 UI/UX 规范与设计验收清单落地 | 产品 + UIUX + QA |
2026-03-27 | SUP-003 | DQA P0=0,P1 通过率>=95% | docs/supply_uiux_design_spec_v1_2026-03-25.md |
| XR-004 | 业主 SLA/申诉/赔付条款并入门禁验收 | 产品 + CS + FIN |
2026-03-28 | XR-002, XR-003 | 条款可执行可测且签字确认 | docs/product/owner_sla_dispute_compensation_rules_v1.md |
| XR-005 | 四专家再次对齐复核并形成发布结论 | ARCH + QA + 产品 + UIUX |
2026-03-28 | XR-001~XR-004 | 复核结论明确(GO/CONDITIONAL GO/NO-GO) | review/multi_expert_alignment_recheck_v1_2026-03-25.md |
4.9 Workstream I:数据库与依赖质量闭环(新增)
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| DB-001 | 跨域核心表基线落地(Core/IAM/Auth/Billing/Audit) | ARCH + PLAT |
2026-03-27 | XR-001 | platform_core_schema_v1.sql 可执行且评审通过 |
sql/postgresql/platform_core_schema_v1.sql |
| DB-002 | 供应域加密/单位/审计字段与索引补齐 | PLAT + QA |
2026-03-28 | DB-001 | patch 可幂等执行,关键查询计划不回退 | sql/postgresql/supply_schema_v1_patch_2026-03-27.sql |
| DB-003 | 数据模型与迁移策略文档并入 SSOT | ARCH |
2026-03-28 | DB-001, DB-002 | 迁移顺序、回滚策略、验收清单完整 | docs/database_domain_model_and_governance_v1_2026-03-27.md |
| DEP-001 | 依赖兼容审计四件套接入发布流程 | PLAT + SEC |
2026-03-28 | COMP-005 | SBOM/锁差异/兼容矩阵/风险清单缺一阻断 | docs/dependency_compatibility_audit_baseline_v1_2026-03-27.md |
| DEP-002 | 分阶段质量门禁(G0-G5)接入 CI | QA + PLAT |
2026-03-29 | DEP-001, XR-002 | M-018 与 M-019 自动计算并阻断 |
CI 记录 + Gate 汇总 |
| DEP-003 | 需求-设计-测试漂移日检机制上线 | PMO + QA |
2026-03-29 | DEP-002 | 发现漂移 24h 内闭环,周报可追踪 | reports/design_drift_daily_*.md |
4.10 Workstream J:token 运行态实现与验收闭环(TOK,新增)
| 任务ID | 任务 | Owner | 截止日期 | 依赖 | 验收标准 | 证据产物 |
|---|---|---|---|---|---|---|
| TOK-001 | token 能力最小实现清单冻结(签发/校验/吊销/续期/审计) | ARCH + SEC + PLAT |
2026-03-28 | SUP-002 | 功能边界、接口与状态机冻结,禁止再口头变更 | docs/token_runtime_minimal_spec_v1.md |
| TOK-002 | 平台鉴权与 token 校验中间件实现(仅平台凭证入站) | PLAT + SEC |
2026-03-30 | TOK-001 | 外部请求必须通过平台凭证校验,覆盖率=100% | 开发阶段:docs/token_auth_middleware_design_v1_2026-03-29.md + docs/platform_token_api_contract_openapi_draft_v1_2026-03-29.yaml;联调阶段:实现代码 + 单测报告 |
| TOK-003 | token 生命周期实现(签发/短期TTL/吊销/轮换) | PLAT |
2026-03-31 | TOK-001 | 生命周期状态可追踪,吊销生效延迟满足阈值 | 开发阶段:docs/token_lifecycle_audit_test_assertions_v1_2026-03-29.md;联调阶段:实现代码 + 集成测试报告 |
| TOK-004 | 安全审计与事件入库(签发/鉴权失败/吊销/越权) | SEC + PLAT |
2026-03-31 | TOK-002, TOK-003 | 审计事件完整入库,可按租户/角色追踪 | 开发阶段:docs/token_lifecycle_audit_test_assertions_v1_2026-03-29.md;联调阶段:审计表样例 + 查询结果 |
| TOK-005 | 凭证边界联调(SUP-007 合并复测) | SEC + QA |
2026-04-01 | TOK-002~TOK-004 | M-013~M-016 在 staging 实测全部达标 | 开发阶段:scripts/supply-gate/tok005_boundary_dryrun.sh + reports/archive/gate_verification/tok005_dryrun_*.md;联调阶段:tests/supply/sec_sup_boundary_report_2026-03-30.md(staging回填) |
| TOK-006 | staging 一键回归(SUP-004~SUP-007 + TOK) | QA + PLAT |
2026-04-01 | TOK-005 | 全链路通过且无 mock 依赖 | 开发阶段:scripts/supply-gate/tok006_gate_bundle.sh + scripts/ci/superpowers_stage_validate.sh + reports/archive/gate_verification/tok006_gate_bundle_*.md + reports/archive/gate_verification/superpowers_stage_validation_*.md + reports/archive/gate_verification/tok006_release_decision_onepager_template_v1_2026-03-30.md;联调阶段:reports/archive/gate_verification/sup_run_all_staging_*.log + 实测单页判定报告 |
| TOK-007 | 发布门禁复审(并入 EXP-006 决议) | ARCH + QA + SEC |
2026-04-03 | TOK-006 | F-04 关闭,生产决议可重新评估 | 开发阶段:scripts/ci/tok007_release_recheck.sh + scripts/ci/final_decision_consistency_check.sh + scripts/ci/tok007_generate_final_decision_candidate.sh + review/outputs/tok007_release_recheck_*.md(活文档只允许引用当时明确标记为现行稿的最新一版,旧批次一律按历史快照处理) + review/outputs/final_decision_candidate_from_tok007_*.md(同前) + reports/archive/gate_verification/final_decision_consistency_*.md + reports/archive/gate_verification/tok007_generate_candidate_*.log;联调阶段:review/final_decision_2026-03-31.md(复审回填) |
5. 验收门禁(每日/每周)
5.1 Daily Gate(每日 18:00)
- 高危配置扫描是否全部通过。
- 兼容 Gate 失败数是否为 0。
- 账务冲突率是否 <= 0.01%。
query_key_external_reject_rate_pct是否 = 100%(否则即 P0)。platform_credential_ingress_coverage_pct是否 = 100%(否则即 P0)。supplier_credential_exposure_events是否 = 0(非0即 P0)。direct_supplier_call_by_consumer_events是否 = 0(非0即 P0)。route_mark_coverage_pct是否 >= 99.9%(不足即禁止升波)。- 迁移异常是否在 15 分钟内完成用户通知(未达标即 P1)。
- 契约漂移检测是否通过(未通过即阻断发布)。
- 供应侧 UI Gate 是否全绿(
UI-SUP-ACC-* / UI-SUP-PKG-* / UI-SUP-SET-*)。 - 供应侧凭证边界专项(
SEC-SUP-*)是否全绿(失败即 P0)。 - 四专家整改链路(XR-001~XR-003)是否全绿(未完成即禁止进入 SUP-008 结论环节)。
- 数据库补丁任务(DB-001~DB-003)是否按阶段达成(未完成即禁止升波)。
- 依赖兼容审计四件套是否完整(缺任一项即阻断发布)。
- 分阶段质量门禁
M-018/M-019是否持续 = 100%(否则回退到失败阶段)。 - token 运行态链路(TOK-002~TOK-006)是否完成(未完成即禁止生产 GO)。
5.2 Weekly Gate(2026-03-24 / 2026-03-31)
- 是否满足 M2 / M5 里程碑验收条件。
- 是否触发 P0 事件(触发则冻结升级)。
- 凭证边界指标(M-013~M-016)是否连续 7 天达标。
- 是否完成回滚演练并达到 30 分钟恢复目标。
- 是否完成当周专家评审并关闭必须整改项。
- 供应侧 Gate(SUP-004~SUP-008)是否完成并出具结论。
- 四专家复核链路(XR-001~XR-005)是否完成并形成签署结论。
- DB/依赖质量链路(DB-* / DEP-*)是否全量关闭。
- 依赖兼容审计指标
M-017是否连续 7 天达标。 - 阶段质量与追踪覆盖指标
M-018/M-019是否连续 7 天达标。 - token 运行态审计缺口(
TOK-REAL-001~003)是否全部关闭。
6. 风险与阻断规则
| 触发条件 | 等级 | 处理动作 |
|---|---|---|
| 账务错误、双流拼接、大面积协议失败 | P0 | 立即回滚,冻结发布,24h 内复盘 |
| 上游凭证泄露、需求方绕过平台直连供应方、平台凭证入站覆盖不足 | P0 | 立即回滚,冻结发布,启动安全应急并完成法务告警 |
| 供应侧结算状态跳态、提现资金对不平、按钮权限越权 | P0 | 冻结供应侧发布链路,执行资金核对与权限审计 |
| 兼容回归影响部分租户 | P1 | 暂停升波,48h 内修复并补测 |
| 非关键指标偏差 | P2 | 记录到 backlog,下迭代修复 |
7. 证据包目录规范(建议)
立交桥/
evidence/
2026-03-31-risk-control/
gate-reports/
supply-gate/
security-scans/
rollback-drill/
dashboards/
review/
所有任务验收必须至少提供:
- 原始执行日志。
- 指标/截图证据。
- 结论与责任人签字(电子审批记录)。
8. 启动会议议程(30 分钟模板)
- 确认实名 RACI 与 on-call(按第2章映射执行)。
- 确认 P0 红线(含凭证边界)及回滚授权链路。
- 确认 M1-M5 日期不变。
- 锁定每日站会与每周评审时间。